Navigating through Fragility
World Bank, Washington, DC
Document overview
Original summaryThis World Bank Quick Note examines innovative procurement strategies used in two education projects in post-conflict Iraq, highlighting how tailored approaches can achieve effective service delivery in fragile states. The document covers the Emergency Textbook Provision Project, which involved printing and distributing 69 million textbooks to 6 million students, and the Marshlands School Construction Project, which built 36 schools in southern Iraq. Key methods include opening markets to international competition, decentralizing procurement authority, strengthening local capacity through training, and engaging local communities and NGOs. The note reports significant outcomes such as cost savings from international competitive bidding, standardized procurement procedures, and enhanced local ownership and employment. It is intended for development practitioners, policymakers, and procurement specialists working in fragile and conflict-affected environments, offering practical insights into balancing risk management, flexibility, and market understanding to achieve project goals.
Key points
- The Emergency Textbook Provision Project used a mix of international and national competitive bidding to reduce costs and improve delivery, achieving lower unit prices through international competition.
- The Marshlands School Construction Project decentralized procurement to local municipalities, encouraging local company participation and community buy-in, which was critical for project success.
- Capacity building measures, including training and on-the-job support, were essential for enabling local Ministry of Education staff to manage procurement and project activities effectively.
- The projects demonstrated that adapting procurement strategies to local conditions, such as using available paper stocks and dividing contracts into smaller lots, can overcome challenges in fragile contexts.
- The document highlights the importance of flexibility, realistic risk management, and a keen understanding of the market in achieving successful procurement outcomes in conflict-affected states.
Written by DocuLuma editors from the document's full text.

Page 1 of 4 · Preview

Page 2 of 4 · Preview

Page 3 of 4 · Preview

Page 4 of 4 · Preview
The full document has 4 pages. Downloads happen on the original source site.
Text excerpt
Excerpted from the original document (first part). Download the file or visit the source for the complete text.
X1` Navigating through Fragility: Procurement Solutions for Iraqi Education Elisa Mosler, Nazaneen Ismail Ali, and Rachel Lipson1 Introduction: While the Iraqi education system was widely regarded as one of the best in the Middle East and enjoyed near-universal primary enrollment until the 1980s, the next decade marked a serious downturn in results. Beginning in the 1990s, the education system in Iraq deteriorated sharply as two decades of conflict and economic sanctions took their toll. The sector witnessed low primary and secondary enrollment and attendance, outdated curriculum content, and deteriorating learning outcomes.
Behind this was a collapse in public investment in education and a resulting standstill in policy and system development in the sector. After the 2003 regime change, the new government had many critical service delivery needs and was struggling to meet these. Among the most urgent were those in education. In order to get children back to school, the government needed large, fast, and quality investments in the education system. $100 million was allocated to the education sector under the World Bank Iraq Trust (ITF), set up jointly by the World Bank Group (WBG) and the United Nations Development Group (UNDG) to administer donor funding for Iraqi reconstruction.
However, in order to implement these investments efficient and effective public contracting and purchasing processes were needed. This Quick Note summarizes how innovative approaches to procurement led to exemplary service delivery results in Iraq’s education sector. The focus is on two breakthrough achievements: large-scale 1 The authors are all members of the Public Integrity and Openness Department of the Governance Global Practice, textbook printing and delivery, under the Emergency Textbook Provision Project and school construction in the newly rehabilitated marshlands of Southern Iraq under the Marshlands School Construction Project.
By developing a unique strategy for procurement that was responsive to local conditions, the Bank was able to support the government in issuing printing contracts, secure book delivery arrangements, and acquire the construction materials and supplies needed to achieve the projects’ development objectives. Iraqi marshlands areas in the 3 governorates of Basrah, Thi Qar and Missan. Portfolio implementation in a fragile and conflict- affected state (FCS) like Iraq is not business as usual and calls for a delicate balance of realism, effective risk management, and flexibility.
Given the insecurity and weakened capacity at the time, the Bank made sure that these concepts, along with a keen understanding of the market, were key tenets of its program. supporting the MENA region. This note was prepared under the guidance of and clearance by, Yolanda Tayler, Practice Manager. June 2015 – Number 146 P ub lic D is cl os ur e A ut ho riz ed P ub lic D is cl os ur e A ut ho riz ed P ub lic D is cl os ur e A ut ho riz ed P ub lic D is cl os ur e A ut ho riz ed June 2015 · Number 146 2 Emergency textbook provision project: Among others, an urgent reform in the post 2003 era was revisions to the country’s national curriculum.
This required a set of primary and secondary school textbooks to be updated, printed and delivered across the country. A grant of US$40 million was given to the Iraqi Ministry of Education (MOE) to finance the printing and distribution of approximately 69 million textbooks, benefitting 6 million students for the 2004- 2005 school year. Before the war, the Government of Iraq had used the same set of textbook printers and suppliers for decades without competitive methods to award contracts. As a result, local printing houses dominated the textbook market with high prices, and unreliable delivery and quality.
Moreover, given the ongoing emergency situation in the country, other risks to procurement were identified throughout the project. For instance, Iraq does not have a real procurement law2 or, at the time, standard bidding documentation.
Both of these factors impacted efficiency and left space for potential corruption.3 Other risks included: The inability of Bank staff to supervise the projects in the field due to the security situation; The weak capacity of the project management team in procurement and management of large contracts; The high risk and weak control environment; The low capacity of local companies to provide the needed supplies; Lack of interest of international contracting companies to do business in the country because of security restrictions; Major delays in implementation because of the lack of experience in procurement planning in the ministry; Faced with the time-sensitive task of reprinting millions of textbooks within a few months and in fragile security conditions, an urgent intervention was needed.
To address the identified risks, a number of measures were taken to facilitate effective implementation. First, the team ensured that World 2 CPA Order 87, imposed by the transitional authority, is not generally regarded as applicable and is for the most part ignored by practitioners. Bank procurement guidelines and the Iraq Master Implementation Manual (MIM) were followed. Second, a local Bank consultant based in Iraq assisted in the supervision of the project and conducted spot physical inspections. Bank staff from outside Iraq also closely supervised the procurement. Third, a dedicated and qualified procurement manager was assigned to manage the project.
Fourth, the project design was kept simple. And fifth, the team introduced flexibility in bidding documents to encourage international and local bidders. In addition, to meet service delivery needs, the Bank helped the government introduce a number of important changes to the way that the Ministry of Education (MOE) managed procurement. These changes would increase supplier competition, reduce supplier prices, and increase transparency while also building MOE capacity.
The measures taken included: Opening the market to international competition: Based on the assessment of the capacity of the local printing industry to deliver large quantities of textbooks within a very short time-frame, the decision was made to use both International Competitive Bidding (ICB) and National Competitive Bidding (NCB). The Bank used regional newspaper advertisements (in neighboring countries) and other methods to attract new suppliers to take part in the bidding process for text book printing. Procurement was carefully packaged to encourage international as well as local bids.
Use of stocks of paper procured by the previous government: Without this, local printers could not have received paper deliveries in time to meet printing and distribution deadlines for the 2004- 2005 academic year. Dividing printing contracts between those involving printing and distribution only (paper supplied by MOE), and contracts requiring the procurement of paper: The number of lots for printing-only contracts was determined by the amount of paper available in Baghdad, and adjusted at appraisal when evidence of more paper came to light.
3 Iraq’s vulnerability to corruption is demonstrated by the country’s poor rankings in Transparency International’s Corruption Perception Index, the lowest of all countries in the region June 2015 · Number 146 3 Strengthening MOE capacity: Frequent training, skills transfer and on–the-job handholding was provided to the project team and MOE staff on procurement and project management both before and during project implementation. These actions had significant effects, most notably: Lower Prices: The use of ICB attracted international firms (mainly Jordanian and Lebanese), and brought millions in cost savings through lower unit costs.
In the first round of procurements, the unit costs of textbooks printed through the NCB contracts were higher than the unit costs obtained through ICB. As a result, the MOE used ICB for the second round and Iraqi …
Related documents

Kyrgyz Republic Public Expenditure Review Policy Notes : Public Wage Bill
Washington, DC
31 p. · PDF · 937.4 KB

Trade, Foreign Direct Investment, and International Technology Transfer : A Survey
World Bank, Washington, DC
50 p. · PDF · 3.1 MB

Girls' Education in the 21st Century : Gender Equality, Empowerment, and Economic Growth
Washington, DC : World Bank
346 p. · PDF · 2.3 MB

Why Should We Care About Care?
World Bank, Washington, DC
82 p. · PDF · 2 MB

How the World Bank Supports Adaptive Social Protection in Crisis Response
Washington, DC: World Bank
181 p. · PDF · 9.4 MB

Enterprise Surveys : Guyana Country Profile 2010
Washington, DC
15 p. · PDF · 785.4 KB