Results Monitoring in Health, Nutrition, and Population : The Experience of the Africa Region 2009/2010
World Bank, Washington, DC
Document overview
Original summaryThis World Bank HNP Discussion Paper, authored by Gayle H. Martin, Benjamin Loevinsohn, and Eriko Saito, provides an assessment of results monitoring practices within the Africa Region's health, nutrition, and population (HNP) portfolio during 2009/2010. The study combines quantitative analysis of all 52 active Africa HNP projects with qualitative surveys of task team leaders (TTLs) to evaluate the design, implementation, and use of results frameworks. Key findings reveal that while the quality of results framework design has improved, execution during project implementation is often lacking, with only 17% of data collection plans being 'mostly' implemented. The report highlights that projects with better-implemented data collection plans are more likely to discuss progress and use evidence in Implementation Status and Results (ISR) reports. It also identifies weaknesses in tracking outcomes among the poor and in executing planned capacity-building support for monitoring and evaluation. The paper concludes with options for improving results monitoring, such as strengthening data collection plan implementation and enhancing capacity building. This document is valuable for development practitioners, project managers, and policymakers involved in M&E, particularly those working in health, nutrition, and population sectors in Africa, as it offers evidence-based insights and practical recommendations for enhancing accountability and results orientation.
Key points
- The study assessed results monitoring in all 52 active Africa HNP projects, combining quantitative and qualitative methods.
- Only 17% of data collection plans were 'mostly' implemented, indicating significant gaps in execution.
- Projects with better-implemented data collection plans were more likely to discuss progress and use data in ISR ratings.
- Tracking outcomes among the poor remained a persistent weakness across the portfolio.
- Capacity-building support for M&E was planned in most projects but execution was often deficient.
Written by DocuLuma editors from the document's full text.

Page 1 of 58 · Preview

Page 2 of 58 · Preview

Page 3 of 58 · Preview

Page 4 of 58 · Preview

Page 5 of 58 · Preview

You have reached the preview limit
The free preview includes the first 6 pages of 58. Download the original document to read the full content.
⬇ Download documentPage 6 of 58 · End of preview
The full document has 58 pages. Downloads happen on the original source site.
Text excerpt
Excerpted from the original document (first part). Download the file or visit the source for the complete text.
H N P D i s c u s s i o N P a P e R about this series... This series is produced by the Health, Nutrition, and Population Family (HNP) of the World Bank’s Human Development Network. The papers in this series aim to provide a vehicle for publishing preliminary and unpolished results on HNP topics to encourage discussion and debate. The findings, interpretations, and conclusions expressed in this paper are entirely those of the author(s) and should not be attributed in any manner to the World Bank, to its affiliated organizations or to members of its Board of Executive Directors or the countries they represent.
Citation and the use of material presented in this series should take into account this provisional character. For free copies of papers in this series please contact the individual authors whose name appears on the paper. Enquiries about the series and submissions should be made directly to the Editor Homira Nassery ([email protected]) or HNP Advisory Service ([email protected], tel 202 473-2256, fax 202 522- 3234). For more information, see also www.worldbank.org/hnppublica- tions.
THe woRlD baNk 1818 H Street, NW Washington, DC USA 20433 Telephone: 202 473 1000 Facsimile: 202 477 6391 Internet: www.worldbank.org E-mail: [email protected] RESULTS MONITORING IN HEALTH, NUTRITION AND POPULATION The experience of the Africa region 2009/2010 Gayle H. Martin, Benjamin Loevinsohn and Eriko Saito December 2010 P ub lic D is cl os ur e A ut ho riz ed P ub lic D is cl os ur e A ut ho riz ed P ub lic D is cl os ur e A ut ho riz ed P ub lic D is cl os ur e A ut ho riz ed RESULTS MONITORING IN HEALTH, NUTRITION AND POPULATION The experience of the Africa region 2009/2010 Gayle H.
Martin, Benjamin Loevinsohn and Eriko Saito Africa Region The World Bank December, 2010 ii Health, Nutrition and Population (HNP) Discussion Paper This series is produced by the Health, Nutrition, and Population Family (HNP) of the World Bank's Human Development Network (HDN). The papers in this series aim to provide a vehicle for publishing preliminary and unpolished results on HNP topics to encourage discussion and debate.
The findings, interpretations, and conclusions expressed in this paper are entirely those of the author(s) and should not be attributed in any manner to the World Bank, to its affiliated organizations or to members of its Board of Executive Directors or the countries they represent. Citation and the use of material presented in this series should take into account this provisional character. Enquiries about the series and submissions should be made directly to the Editor, Homira Nassery ([email protected]). Submissions undergo informal peer review by selected internal reviewers and have to be cleared by the TTL's Sector Manager.
The sponsoring department and author(s) bear full responsibility for the quality of the technical contents and presentation of material in the series. Since the material will be published as presented, authors should submit an electronic copy in the predefined template (available at www.worldbank.org/hnppublications on the Guide for Authors page). Drafts that do not meet minimum presentational standards may be returned to authors for more work before being accepted. For information regarding the HNP Discussion Paper Series, please contact Homira Nassery at [email protected], or 202-522-3234 (fax).
© 2011 The International Bank for Reconstruction and Development / The World Bank 1818 H Street, NW Washington, DC 20433 All rights reserved.
iii Health, Nutrition and Population (HNP) Discussion Paper Results Monitoring in Health, Nutrition and Population The Experience of the Africa Region 2009/2010 Gayle Martin, Benjamin Loevinsohn and Eriko Saito Health, Nutrition and Population, Africa Region, The World Bank, Washington DC, USA Paper prepared for Africa HNP (AFTHE) The World Bank, Washington D.C., U.S.A., September 15, 2010 Abstract: The Bank’s shareholders and stakeholders are increasingly demanding better accountability for results and progress toward achieving the Millennium Development Goals (MDGs).
In response, the various reforms and initiatives toward an enhanced results orientation have increased in prominence, yet actual progress has lagged. The purpose of the study was to provide an assessment of results monitoring in the Africa HNP portfolio. The report focuses on results monitoring and less on evaluation, because tracking results is one of the most basic requirements to improve accountability for results and a key precursor to evaluation. The study combined quantitative and qualitative techniques.
The quantitative analysis assessed the design of results frameworks, its implementation and use in all 52 active Africa HNP projects; the qualitative assessment surveyed the experiences of task team leaders (TTLs) and aimed to identify some incentives, as well as some innovative and strategic actions, to improve results monitoring. The study found that the attention to results monitoring during a project’s lifespan is uneven. While there is some improvement in the quality of results framework design, the execution of results frameworks during project implementation is lacking. Tracking outcomes among the poor has remained a weakness.
Only 17 percent of data collection plans were ―mostly‖ implemented and those projects with data were more likely to discuss progress and make reference to data in deciding on ratings. The extent to which data collection plans were implemented had a direct relationship with the number of indicators in the design. The implementation of data collection plans also determined the extent to which there is any discussion of results in the Implementation Status and Results Report (ISR) and use of evidence used to underpin the ratings used to track project performance.
Although assessments of capacity in results monitoring and evaluation were conducted in only a quarter of projects, most projects planned to support capacity building. There were however deficiencies in the extent to which the planned support was executed. Keywords: results monitoring, monitoring and evaluation, project performance, results. iv Disclaimer: The findings, interpretations and conclusions expressed in the paper are entirely those of the authors, and do not represent the views of the World Bank, its Executive Directors, or the countries they represent. Correspondence Details: Gayle H.
Martin, The World Bank, 1818 H Street, NW, Washington, DC 20433, USA, (202) 473-7862, [email protected], www. worldbank.org v Table of Contents ACKNOWLEDGEMENTS ........................................................................................... vii ABBREVIATIONS AND ACRONYMS ........................................................................ ix EXECUTIVE SUMMARY ............................................................................................. xi 1. BACKGROUND AND CONTEXT .............................................................................
1 RATIONALE ...................................................................................................................... 1 RESULTS MONITORING AND M&E .................................................................................... 2 PREVIOUS STUDIES ON RESULTS MONITORING AND EVALUATION ..................................... 3 IMPROVING THE METHODOLOGY OF THE BANK’S PROJECT REVIEWS ................................ 4 2. OBJECTIVES AND SCOPE ....................................................................................... 5 OBJECTIVES ......................................................................................................................
5 ANALYTIC STRATEGY ....................................................................................................... 5 3. RESULTS ...................................................................................................................... 7 INTER-RATER AGREEMENT ............ …
Related documents

Ghana : 2005 External Review of Public Financial Management, Volume 1, Main Report
Washington, DC
62 p. · PDF · 5.1 MB

Impact of Universal Accessibility in Tertiary Infrastructure Projects of Indonesia and the KOTAKU Project
Washington, DC: World Bank
51 p. · PDF · 1.8 MB

Climate Shocks and Their Effects on Food Security, Prices, and Agricultural Wages in Afghanistan
Washington, DC: World Bank
38 p. · PDF · 1.6 MB

Welfare Analysis of Changing Notches
Washington, DC : World Bank
70 p. · PDF · 2.8 MB

Pinpointing Poverty in Hungary
World Bank, Washington, DC
2 p. · PDF · 1.6 MB

VAT Rate Structures in Theory and Practice
World Bank, Washington, DC
26 p. · PDF · 655.6 KB