Promoting Renewable Energy through Auctions : The Case of Brazil
World Bank, Washington, DC
Document overview
Original summaryThis World Bank knowledge note examines Brazil's use of electricity auctions to promote renewable energy, focusing on the evolution of wind power development through two distinct stages. It provides a data-driven analysis of the auction scheme's strengths and weaknesses, based on Brazil's extensive experience since its 2004 market reform, which has contracted 58 GW of new capacity. The document covers key topics including auction design, risk allocation, supply-demand balancing, and the coordination of generation and transmission planning. It highlights critical data such as the rise in declared capacity factors from 44% in 2009 to over 50% in 2012, and the severe delays affecting more than half of wind plants in early auctions due to transmission issues. The note also discusses the positive outcomes, including economic development, lower generation prices (falling to about $50/MWh after 2011), and increased competition. It concludes by outlining the challenges Brazil faced in the second stage, such as overoptimistic investor performance estimates and the need for more reliable system planning. This document is suitable for energy policymakers, regulators, and analysts interested in auction mechanisms for renewable energy, offering practical insights into policy design and adaptation in a complex environment.
Key points
- Brazil's wind energy auctions evolved in two stages, with the first stage successfully attracting investment but leading to overestimated performance and supply-demand imbalances.
- Declared capacity factors by wind investors rose from an average of 44% in 2009 to over 50% in 2012, much higher than global norms, indicating aggressive bidding.
- More than half of wind plants contracted in the first three auctions experienced severe delays (over a year) due to transmission line and substation construction problems.
- Wind power development contributed to lower auction prices for new generation, falling to about $50/MWh after 2011, and fostered the growth of the wind equipment industry in Brazil.
- The government revised auction design in 2013 to address risk allocation and improve the reliability of wind project performance assessments.
Written by DocuLuma editors from the document's full text.

Page 1 of 8 · Preview

Page 2 of 8 · Preview

Page 3 of 8 · Preview

Page 4 of 8 · Preview

Page 5 of 8 · Preview

You have reached the preview limit
The free preview includes the first 6 pages of 8. Download the original document to read the full content.
⬇ Download documentPage 6 of 8 · End of preview
The full document has 8 pages. Downloads happen on the original source site.
Text excerpt
Excerpted from the original document (first part). Download the file or visit the source for the complete text.
The boTTom line The Brazilian experience with wind energy auctions illustrates that even carefully designed policies often must be reconsidered in the light of a complex and changing environment. Many considerations need to be taken into account to ensure competitive prices while also delivering the required renewable energy supply. Gabriela Elizondo Azuela is a senior energy specialist in the World Bank’s Energy Practice. Luiz Barroso is a managing director at PSR in Brazil. Gabriel Cunha is a consultant in international energy systems and energy policies at PSR. Promoting Renewable energy through Auctions: The Case of brazil Why is this case interesting?
brazil’s initial success with developing wind capacity had unforeseen consequences Electricity auctions are at the core of the regulatory framework that Brazil adopted after reforming its electricity market in 2004 (Maurer and Barroso 2011). Since then, periodic energy auctions have made possible the construction of 58 GW of new generation capacity (46 percent hydropower and 29 percent from other renewable sources), through about $350 billion in long-term contracts.1 This extensive experience allows a quantitative data-based assessment of the strengths and weaknesses of the country’s auction scheme and its application to renewable energy development.
Wind power development is especially interesting because it has progressed in two very distinct stages, both using auctions (Cunha, Barroso, and Bezerra 2014; Cunha and others 2012). The first stage was marked by a strong will to promote the development of nonconventional renewable sources of energy. Even though Brazil has historically relied on the continuous development of large hydropower generation—hydropower represented 70 percent of the country’s total installed capacity of 120 GW at the end of 2012—large amounts of small hydro, wind, and biomass potential remained untapped.
The main challenge of this first stage was to create conditions that would allow those sources not only 1 All amounts in this document have been updated according to Brazilian inflation indexes (either IPCA or IGP-M, depending on the indexing terms of each power purchase agreement) and converted to U.S. dollars at a rate of 2.2 Brazilian real to the dollar. to emerge in the energy mix, but possibly to become competitive with conventional sources.
Contracts were specifically designed to accommodate the characteristics of individual technologies, aiming to attract more investors by offering an attractive product that would shield them from several unmanageable risks—such as inflation and the uncertainty of variable generation. The results of the first stage were wildly successful: The renew- able auctions were very competitive, drawing large investments from both the public and private sectors,2 and allowing consumers to benefit from cleaner energy at lower prices. However, the success of the wind auctions brought other chal- lenges.
Critics complained that the terms offered in contracts were too generous for investors and that, as a result, generators had an incentive to bid aggressively and to make unrealistic promises about their plants’ likely performance. Note that regular energy auctions in Brazil have the express objective of ensuring adequate system expansion.
While this is an important concern in any country where demand for electricity is growing rapidly (over the past decade, Brazil’s demand has grown by 4.3 percent per year, on average), in Brazil there is also the need to maintain an optimal management of hydropower reserves: If the system is undersupplied (that is, if there is not enough firm generation capacity to meet demand), reservoirs will deplete faster, which could increase the risk of energy shortages.
Therefore, when the first stage of wind farm development through 2 The government’s role in the auctions was felt through the direct participation of state- owned utilities as well as the indirect participation of the Brazilian development bank, which offered attractive loans to investors.
A k n o w l e d g e n o t e s e r i e s f o r t h e e n e r g y p r A c t i c e 2014/13 A k n o w l e d g e n o t e s e r i e s f o r t h e n e r g y & e x t r A c t i v e s g l o b A l p r A c t i c e 2 P r o M o T i n g r e n e w a B l e e n e r g y T h r o u g h a u c T i o n s : T h e c a s e o f B r a z i l “Systematic overestimation of the performance of wind plants threatened to further upset the system’s supply- demand balance.” auctions progressed to the point where wind-based capacity began to constitute a significant fraction of system expansion, security of supply became a concern.
These concerns defined the second stage of wind power development in Brazil, which is the main topic of this note. The Brazilian government began to tackle some of these issues in 2013, revising some aspects of the auction design introduced in 2009 and seeking an optimal allocation of risk in the contracts offered to wind producers. What challenge did brazil face? For system planning purposes, the performance of auctioned wind projects needed to become more reliable Challenges introduced in the first stage of wind power development had to be solved in the second.
The chief challenges were (i) the Brazilian system had to be able to balance supply and demand more accurately; (ii) investors were overoptimistic about the amount of electricity they would be able to generate; and (iii) the government’s arrangements for coordinating the planning of generation and transmission left too little room for error. The Brazilian system needed a more accurate assess- ment of its supply-demand balance. Typically, the country’s security of supply is ensured through the purchase of firm energy certificates (FECs) by all consumers. (Utilities are responsible for procuring FECs on behalf of regulated consumers).
The government issues FECs to generators in accordance with their capability to generate reliable energy. As wind power comes to constitute a larger and larger share of Brazil’s generation system, the technology inev- itably takes on a greater role in the security of supply. However, the current method of calculating FECs for wind plants is very simplistic and does not take into account how the wind power injections interact and synchronize with the system as a whole. Because this mechanism does not represent the true expected contribution of wind plants when integrated with a large hydro system, the task of determining the system’s new capacity needs becomes much harder.
Investors were very aggressive in the certification of their wind generation capabilities. The contract designed for wind producers offered attractive settlement rules that were aimed at protecting generators against unforeseeable wind fluctuations. Even if yearly average generation deviated from the amount prom- ised in the auction, generators suffered only mild penalties, and the full settlement of differences was carried out only once every four years. These rules may have encouraged aggressive certification of wind production on the part of investors.
Indeed, as illustrated in figure 1, average capacity factors declared by wind investors in the auctions rose from an average of 44 percent in 2009 to more than 50 percent in 2012—both figures being much higher than most wind production sites in the world. Systematic overestimation of the performance of wind plants threatened to further upset the system’s supply-demand balance. The government’s scheme to coordinate generation and transmission planning faced difficulties.
Another benefit offered to the participants in early energy auctions was that the government was poised to assume responsibility for organizing the reinforce- ments and expansions to the grid that were needed to accom- modate the new generation contracted through auction (Rudnick 100 90 80 70 60 50 40 En er gy s al e p ri ce ( U S $/ M W h ) 2009 2010 2011 2012 20 6055504540353025 65 Capacity factor (percent) …
Related documents

Participation in WTO Dispute Settlement : Complainants, Interested Parties, and Free Riders
Published by Oxford University Press on behalf of the World Bank
24 p. · PDF · 142.4 KB

Growth and Volatility Analysis Using Wavelets
World Bank, Washington, DC
33 p. · PDF · 448.9 KB

Integrating the Poor into Universal Health Coverage in Vietnam
World Bank, Washington DC
36 p. · PDF · 1.5 MB

Arab Republic of Egypt : Detailed Assessment Report on Anti-Money Laundering and Combatting the Financing of Terrorism
Washington, DC
223 p. · PDF · 1.7 MB

Mexico : Accounting and Auditing
Washington, DC
21 p. · PDF · 495.9 KB

Tenure Security and Land-Related Investment : Evidence from Ethiopia
World Bank, Washington, DC
36 p. · PDF · 1.6 MB