Sri Lanka PPP Diagnostic Note
World Bank, Washington, DC
Document overview
Original summaryThe World Bank's Sri Lanka PPP Diagnostic Note provides an in-depth analysis of the challenges and opportunities in Sri Lanka's infrastructure development through Public-Private Partnerships (PPPs). It highlights the country's fiscal constraints, overreliance on public finance, lack of project prioritization, and limited institutional capacity as key issues. The note suggests optimizing public resources, establishing an apex institutional framework, institutionalizing a PPP unit, and improving the policy environment as key actions to enhance PPPs in Sri Lanka. It is intended for policymakers, investors, and stakeholders interested in infrastructure development and PPPs in Sri Lanka.
Key points
- Sri Lanka faces fiscal constraints requiring alternative financing options like PPPs for infrastructure needs.
- Overreliance on public sector financing for PPP projects hinders private sector involvement.
- Lack of project prioritization and feasibility assessments hampers effective infrastructure development.
- Multiple agencies with overlapping functions create uncertainty for investors.
- Limited institutional capacity and overreliance on unsolicited proposals affect PPP effectiveness.
Written by DocuLuma editors from the document's full text.

Page 1 of 10 · Preview

Page 2 of 10 · Preview

Page 3 of 10 · Preview

Page 4 of 10 · Preview

Page 5 of 10 · Preview

You have reached the preview limit
The free preview includes the first 6 pages of 10. Download the original document to read the full content.
⬇ Download documentPage 6 of 10 · End of preview
The full document has 10 pages. Downloads happen on the original source site.
Text excerpt
Excerpted from the original document (first part). Download the file or visit the source for the complete text.
THE WORLD BANK GROUP - South Asia Sri Lanka PPP Diagnostic Note 21 Accelerating infrastructure investment through PPPs Key Findings Fiscal constraints and limited budget resources will require the Government of Sri Lanka to explore and consider alternative financing options to address the country’s infrastructure needs. One option to address these constraints is to mobilize private sector financing through the use of Public Private Partnerships (PPPs). However, it is important to note that PPPs have direct and indirect fiscal and financial implications which need to be assessed on a case by case basis and fully understood by participating agencies and policy makers.
Overreliance on public finance. In Sri Lanka today, many projects that are suitable candidates for PPP procurement are typically being financed through the public sector, with the public sector funds often being sourced through sovereign loans backed by sovereign guarantees. Private sector financing is only sought in cases where a project is unable to secure public funding. This practice is partly a result of the lack of a framework that can help line ministries determine the most appropriate method of procurement and financing (public sector versus PPP) at the project inception stage. Lack of project prioritization.
The Government’s Western Region Megapolis Program consists of over 160 individual projects with an estimated investment volume of US$40 billion. In addition, there are a large number of other projects identified by various agencies at the national level. However, there is no framework to prioritize such projects and, more importantly, many of these projects are not being properly assessed for feasibility or readiness for implementation. Multiple agencies with overlapping functions. There is currently no clear assignment of responsibilities among the various government agencies engaged in promoting PPPs. As a result, different agencies are independently pursuing PPP projects.
The absence of a cohesive framework to govern the institutional mandates, responsibilities and inter-agency decision making processes has created an environment of uncertainty and confusion that is difficult for potential domestic and foreign investors to navigate. Limited institutional capacity. Although in the past there have been several PPPs successfully transacted in the port and power sectors, the current institutional capacity with respect to structuring and procuring PPPs is severely limited. Over reliance on unsolicited proposals.
In recent years, a substantial number of public sector projects have been procured on an unsolicited bid basis which is a practice that can have adverse implications with respect to transparency and value for money considerations. Limited capacity in the debt markets to finance infrastructure projects. There are liquidity (debt volumes and tenors) constraints in the domestic financial markets given the magnitude of investment required. Land valuation issues. A perceived lack of consistency with respect to the allocation and valuation of Government land for investment has implications for a successful PPP program.
P ub lic D is cl os ur e A ut ho riz ed P ub lic D is cl os ur e A ut ho riz ed P ub lic D is cl os ur e A ut ho riz ed P ub lic D is cl os ur e A ut ho riz ed 2 Key Actions Optimize public resources and prioritize investments. To optimize the use of public resources a more systematic process of project prioritization should be adopted. In addition, instituting a mechanism for a detailed economic and financial analysis of each of the prioritized projects as well as having coordinated inter-agency discussions, will help better determine the nature of support (financial and/or non-financial) that may be required from Government. Establish an ‘apex’ institutional framework.
A high-level committee, with representatives from key sectors, should be established. Such an apex institution would have the mandate to review all proposed investments and assess whether they should be financed publicly or be developed through a PPP. An inter-ministerial or cabinet level sub-committee could act as such an apex institution. Institutionalize a PPP unit. Based on the experience in other countries, a specialized PPP unit for the identification, preparation, evaluation and negotiation of PPPs should be considered for the development of PPPs in Sri Lanka. This PPP unit would also provide the necessary analytical support to the proposed apex institution referred to above.
Improve policy environment. Clear and consensus-based policies and guidelines should be established around Public Investment Management and PPPs, with the objectives of enhancing coordination and optimizing the use of public finance. Strengthen procurement guidelines. Sri Lanka’s current public procurement guidelines for PPPs require review and revision, particularly with respect to managing unsolicited bids. Specifically, the mechanisms and procedures for handling unsolicited proposals need to be clarified and strengthened to ensure more effective adherence to the principles of competitive tendering and value for money. Develop a liability management framework.
A liability management framework should be developed that will enable the Government to better manage and track the direct and contingent fiscal liabilities that arise from PPP arrangements. Build PPP capacity and awareness. A consistent understanding of PPPs should be ensured across the various line ministries and government agencies. This can be achieved through training and the use of PPP guide books. The Government should also actively reach out to external stakeholders to encourage an open dialogue about PPPs. Mobilize long term infrastructure finance.
Once a sizeable project pipeline is identified, the Government could consider establishing an infrastructure development financing institution that can help mobilize long-term financing for infrastructure PPPs. THE WORLD BANK GROUP The World Bank | Policy Note | September 2016 - South Asia Sri Lanka: As Things Stand Now 1. Sri Lanka is facing rising fiscal constraints which are likely to limit its capability to invest in public infrastructure. Sri Lanka is a lower-middle-income country with a per capita GDP of USD 3,924 in 2015.
It ranks relatively high (73rd) on the United Nations Human Development Index compared to other developing economies and 107 (up from 113 in 2015) on WBG’s Doing Business Indicator. The banking sector has been strengthening with a 15.9% increase in total assets in 2015 and a 3.2% reduction in non-performing loans. However, Sri Lanka’s credit rating was downgraded by Fitch and put on a negative outlook by S&P in early 2016, due to growing external and fiscal vulnerabilities. Sri Lanka is currently rated B+ (Fitch), B+ (S&P) and B1 by Moody’s.
Although Sri Lanka’s GDP is expected to grow at a robust pace of 5.3% in the medium term with low inflation close to 4%, the fiscal deficit has been increasing and for 2015 it amounted to 7.4% of GDP, significantly exceeding the original budget target of 4.4%. The external current account balance has narrowed to an estimated 2.4% of GDP by end 2015 and public debt has risen to over 70% of GDP. However, despite the narrowing of the current account, the country experienced capital outflows in 2015 and the overall balance of payments has deteriorated.
Actual spending on infrastructure as a percentage of GDP has also been declining and was budgeted to be only 1.6% of GDP in 2015 (USD1.3 billion1 against GDP of USD80.6 billion2). Estimations are that Sri Lanka will need to invest around 7%3 annually to enable the country to achieve a high level of basic services similar to that experienced in more developed economies, or investment around 4% of GDP annually to achieve more modest standards in terms of access and quality of service. The spending of 1.6% of GDP in Sri Lanka for 2015 compares to actual 2015 infrastruc …
Related documents

Participation in WTO Dispute Settlement : Complainants, Interested Parties, and Free Riders
Published by Oxford University Press on behalf of the World Bank
24 p. · PDF · 142.4 KB

Doing Business 2014 Economy Profile : New Zealand
World Bank Group, Washington, DC
106 p. · PDF · 1.2 MB

Malawi Economic Monitor, May 2017
World Bank, Lilongwe, Malawi
49 p. · PDF · 976.6 KB

Gabon Country Economic Memorandum
Washington, DC: World Bank
180 p. · PDF · 4.7 MB

More Than a Pretty Picture : Using Poverty Maps to Design Better Policies and Interventions
Washington, DC: World Bank
308 p. · PDF · 3.9 MB

Thirsty Business
Washington, DC: World Bank
32 p. · PDF · 1.1 MB